Nuovo Construction Update Centre

Beginning of October 2021

  • Site works have now commenced in line with schedule.
  • We have begun clearing the site. This process will take 3 weeks.
  • Estimated settlement time remains at Q4 2022.

 

Mid-October 2021

  • Almost finished clearning and then we will have 3 weeks of fill coming to site (truck every 6 mins for 3 weeks).
  • We are now sold out of Stage 1.
  • We will start laying slabs during the middle of December 2021.
  • Expected settlement is Q4 2022.

November 2021

  • We have finished clearing the site.
  • We have started to bring fill onto the site.
  • Retaining being done as we go.
  • We will start laying slabs during the middle of December 2021.
  • Expected settlement is Q4 2022.

December 2021

  • We will continue to bring fill onto the site.
  • Even with the rain we haven’t lost too much time.
  • Retaining will be done as we go.
  • We will start laying slabs in early January 2022.
  • Expected settlement is Q4 2022.

January 2022

  • We are now retaining and laying the footings and piers in preparation for the slabs to be poured.
  • We have lost some time with rain delays which we will try to get back in the coming months.
  • Retaining will be done as we go.
  • We will start laying slabs mid-February 2022.
  • Expected settlement is Q4 2022.

March 2022

  • We are now moving quickly through the build and getting walls up on Terrace Lots 1-8.
  • We expect to begin pouring slabs in the next two weeks for Terrace Lots 10-18.
  • By the end of next month we will have begun work on the Residences as retaining will be completed.
  • We lost some time due to the floods in February.
  • Expected settlement is now Q1 2023.

April 2022

  •        We are now moving quickly through the build and getting block walls up on Terrace Lots 11-14.

    ·       We expect to begin pouring slabs in the next two weeks for Terrace Lots 15-16.

    ·       First floor framing for Lots 1-8 is almost completed. Ground floor framing for Lots 11-14 will start next week.

    ·       Roofing will start to be installed over the coming weeks.

    ·       Expected settlement Lots 1-18: Q1 2023.

    ·       Expected settlement Lots 19-30: Q1 2023.

May 2022

  •        We are now moving quickly through the build and getting roofs up on Terrace Lots 11-14.

    ·       We expect to begin pouring slabs next week for Terrace Lots 15-20.

    ·       First floor framing for Lots 11 – 14 is almost completed. Ground floor framing for Lots 11-14 has been finished.

    ·       We have started ground works for the Residences including moving the electric power mains underground.

    ·       Expected settlement Lots 1-18: Q1 2023.

    ·       Expected settlement Lots 19-30: Q1 2023.

  •            Expected settlement Lots 50-57: Q1 2023.

June 2022

  • In the next week we will get the roofs up on Terrace Lots 15-16.
  • First floor framing for Lots 15 – 16 is almost complete. Ground floor framing for Lots 15 -16 has been finished.
  • We have started brickworks and cladding on Lots 1-8.
  • Flooring is expected in Lots 1 – 8 at the end of the month.
  • Expected settlement Lots 1-18: Q1 2023.
  • Expected settlement Lots 19-30: Q1 2023.
  • We have started ground works for the Residences including moving the electric power mains underground.
  • We expect to begin pouring slabs this weekend for Terrace Lots 17-20.
  • Expected settlement Lots 50-57: Q1 2023.

July 2022

  • In the next week we will get the roofs up on Terrace Lots 17-20.
  • First floor framing for Lots 17 – 18 is almost complete. Ground floor framing for Lots 21-22 will be finished shortly.
  • We have started brickworks and cladding on Lots 1-8.
  • Flooring is expected in Lots 1 – 8 at the end of the month.
  • Expected settlement Lots 1-18: Q1 2023.
  • Expected settlement Lots 19-20: Q1 2023.
  • We expect to begin pouring slabs for the Residences next month.
  • Expected settlement Lots 50-57: Q1 2023.

August 2022

  • We now have roofs on Lots 1-8 & 11-20.
  • First-floor framing for Lots 21 – 22 is almost complete. Ground floor framing for Lots 23-24 will be finished shortly.
  • We have started brickworks and cladding on Lots 11-20.
  • Flooring is expected in Lots 11 – 20 at the end of the month.
  • Expected settlement Lots 1-18: Q1 2023.
  • Expected settlement Lots 19-20: Q1 2023.
  • We have started groundworks for the Residences.
  • We expect to begin pouring slabs for the Residences this month.
  • Expected settlement Lots 50-57: Early Q2 2023.

September 2022

  • We now have roofs on Lots 1-8 & 11-22.
  • First-floor framing for Lots 23 – 24 is almost complete. Ground floor framing for Lots 25 – 26 will be finished shorty.
  • We have started brickworks and cladding on Lots 21-22.
  • Flooring is expected in Lots 21 – 26 at the end of the month.
  • Expected settlement Lots 1-18: Q1 2023.
  • Expected settlement Lots 19-20: Q1 2023.
  • We have started groundworks for the Residences.
  • We expect to begin pouring slabs for the Residences this month.
  • Expected settlement Lots 50-57: Early Q2 2023.

October 2022

  • We now have roofs on Lots 1-8, 1-22 & 23-26.
  • Roofs are about to go up on Lots 27-30.
  • We have started prepping the Residence lots for slab pouring.
  • Expected settlement Lots 1-8 & 11-18: Q1 2023 – Late January.
  • Expected settlement Lots 19-30: Q1 2023 – Late March.
  • Expected settlement Lots 9-10: Q1 2023 – Late March.
  • We expect to begin pouring slabs for the Residences this month and finish the curb to the exterior of the development.
  • Expected settlement Lots 50-57: Q2 2023 – May.

December 2022

  • We now have roofs on Lots 1-8, 11-30.
  • We are now finishing internals for 19-30.
  • We have started pouring slabs for the Residences and Lots 9 and 10 will be poured in early January.
  • We will begin landscaping for the project in January.
  • Expected settlement call for Lots 1-8 & 11-18: Late February 2023.
  • Expected settlement call for Lots 19-30: Late April 2023.
  • Expected settlement call for Lots 9-10: Late April 2023.
  • Expected settlement call for Lots 50-57: June/July 2023.

February 2023

  • We are nearing internal completion for Lots 1-8 & 11-18.
  • We are now tiling and painting inside Lots 19-30.
  • We are about to install roofs on Lots 9 and 10.
  • We will continue landscaping for Lots 1-8 as settlement approaches.
  • Expected settlement call for Lots 1-8 & 11-18: Late March 2023.
  • Expected settlement call for Lots 19-30: Late May 2023.
  • Expected settlement call for Lots 9-10: Late May 2023.
  • Expected settlement call for Lots 50-57: June/July 2023.

End of February 2023

  • We are nearing practical completion for Lots 1-8 & 11-18.
  • We are still tiling and painting inside Lots 19-30.
  • We are about to install roofs on Lots 9 and 10.
  • We will continue landscaping for Lots 1-8 & 11-18 as settlement approaches.
  • Expected settlement call for Lots 1-8 & 11-18: Mid-March 2023.
  • Expected settlement call for Lots 19-30: Mid-May 2023.
  • Expected settlement call for Lots 9-10: Mid-May 2023.
  • Expected settlement call for Lots 50-57: June/July 2023.

Start of May 2023

• We have now settled Lots 1-8 and 11-18.
• We are still tiling and painting inside Lots 19-30.
• We are now installing roofs on lots 9 and 10 and will begin external cladding next week.
• We will finish off the internal road in the coming weeks and begin to install driveways.
• Lots 1-8 & 11-18: Settled.
• Expected settlement call for Lots 19-30: End-of-July 2023.
• Expected settlement call for Lots 9-10: September 2023.
• Expected settlement call for Residences 50-57: September/October 2023.

Middle of July 2023

  • We are now landscaping Lots 19-30 and completing the finishing touches before builders clean.
  • We are now working internally on Lots 9 and 10.
  • Internal roads are now complete.
  • Expected settlement call for Lots 19-30: Start-of-August 2023.
  • Expected settlement call for Lots 9-10: September 2023.
  • Expected settlement call for Residences 50-57: September/October 2023.
Privacy Settings
We use cookies to enhance your experience while using our website. If you are using our Services via a browser you can restrict, block or remove cookies through your web browser settings. We also use content and scripts from third parties that may use tracking technologies. You can selectively provide your consent below to allow such third party embeds. For complete information about the cookies we use, data we collect and how we process them, please check our Privacy Policy
Youtube
Consent to display content from Youtube
Vimeo
Consent to display content from Vimeo
Google Maps
Consent to display content from Google
Spotify
Consent to display content from Spotify
Sound Cloud
Consent to display content from Sound

Copyright 2022 @ JAM Group