Beginning of October 2021
Mid-October 2021
November 2021
December 2021
January 2022
March 2022
April 2022
We are now moving quickly through the build and getting block walls up on Terrace Lots 11-14.
· We expect to begin pouring slabs in the next two weeks for Terrace Lots 15-16.
· First floor framing for Lots 1-8 is almost completed. Ground floor framing for Lots 11-14 will start next week.
· Roofing will start to be installed over the coming weeks.
· Expected settlement Lots 1-18: Q1 2023.
· Expected settlement Lots 19-30: Q1 2023.
May 2022
We are now moving quickly through the build and getting roofs up on Terrace Lots 11-14.
· We expect to begin pouring slabs next week for Terrace Lots 15-20.
· First floor framing for Lots 11 – 14 is almost completed. Ground floor framing for Lots 11-14 has been finished.
· We have started ground works for the Residences including moving the electric power mains underground.
· Expected settlement Lots 1-18: Q1 2023.
· Expected settlement Lots 19-30: Q1 2023.
Expected settlement Lots 50-57: Q1 2023.
June 2022
July 2022
August 2022
September 2022
October 2022
December 2022
February 2023
End of February 2023
Start of May 2023
• We have now settled Lots 1-8 and 11-18.
• We are still tiling and painting inside Lots 19-30.
• We are now installing roofs on lots 9 and 10 and will begin external cladding next week.
• We will finish off the internal road in the coming weeks and begin to install driveways.
• Lots 1-8 & 11-18: Settled.
• Expected settlement call for Lots 19-30: End-of-July 2023.
• Expected settlement call for Lots 9-10: September 2023.
• Expected settlement call for Residences 50-57: September/October 2023.
Middle of July 2023